The microgrid civil works specification and procurement phase involves the preparation, planning, tendering and contractor selection for the Civil works. This phase is essential for preparing the site work packages and ensuring that all structures, foundations, and necessary civil works are completed to accommodate the microgrid’s electrical and mechanical components.

 

During this phase Island Microgrids with partners prepare the Civil Works Specifications and prepare the RFP’s, the Client selects and manages its Civil Works contractors and Island Microgrids will be on hand to support the Client as required. 

 

Below is a summary of what this phase typically involves and how it would be delivered:

​​

1. Civil Works Specification (Island Microgrids)

During the detail Engineering Design and Planning Phase, Island Microgrids with its partners

generated the detail specifications for the following. 

  • Site Assessment. For the chosen site a final site survey is conducted with geotechnical studies to understand the soil conditions, topography, and other site-specific factors that will influence the design and construction.

  • Foundation Design. Design of the foundations that will support all major components, such as solar panels, energy storage units, control rooms, and transformers.

  • Structural Design: Specifications developed for any required structures, including buildings for housing equipment, protective enclosures, and mounting structures for PV panels.

  • Roads and Access: Design for access roads, pathways, and any other transportation infrastructure needed for construction, maintenance, and operation specified.

  • Drainage and Water Management: Specifications for drainage systems, water management, and erosion control to protect the site from water damage and ensure long-term stability specified.

  • Security and Fencing: Design for fencing, security systems, and access control to protect the microgrid infrastructure specified. 

​

2. Procurement Planning (Island Microgrids)

In collaboration with the Client, Island Microgrids will generate the following.  

  • Procurement Strategy: A strategy for procuring civil works services and materials, including decisions on whether to use in-house teams or contract external civil engineering firms.

  • Schedule: A detailed procurement and construction schedule that aligns with the overall project timeline, including critical milestones for site preparation, foundation work, and building construction.

​

3a. Request for Proposal (RFP) (Island Microgrids)

Island Microgrids with its partners will develop detailed RFP documents for civil works, including scope of work, technical specifications, timelines, and evaluation criteria for the Client to issue to its selected bidding contractors.

 

3b. Tendering Process (Client)

Island Microgrids with its partners will be on-hand to support the Client and its selected bidding

contractors through the following process.

  • Tendering. Client will issue RFPs to qualified contractors and manage the tendering process:

    • Invitation to tender

    • Site visits for prospective bidders

    • Clarifications and responses to bidder questions

    • Bid submission and evaluation

  • Bid Evaluation. Evaluate bids based on technical compliance, experience, cost, and proposed timelines.

  • Contractor Selection: Select contractors based on bid evaluation and negotiate contracts to ensure compliance with project requirements.

 

The civil works specification, procurement, and delivery phase is a critical step in preparing the site for the microgrid’s electrical and mechanical systems. Proper execution during this phase ensures a solid foundation and infrastructure, which is essential for the long-term success and reliability of the microgrid.

​​